| 1 | Electrification of Opalo, Shemun, Hoki and Zekun | | Lamurde LGA | Bengin & Associate Ltd | 1/16/2023 | 243,781,700.09 | 195,025,360.08 | 80% | May-24 | |
| 2 | Construction of Banjiram- Chikila 9.2 KM Road | | Guyuk LGA | A.T Barak Service Ltd | 12/30/2022 | 247,705,968.13 | 198,164,756.50 | 85% | May-24 | |
| 3 | Electrification of Bille, Kpasham Dong | | Demsa LGA | Electromax Engr. Services Ltd | 11/27/2022 | 654,630,306.75 | 638,254,549.08 | 100% | Apr-24 | Awaiting Official Commissioning |
| 4 | Electrification of So'o and Mapeo | | Jada LGA | Electromax Engr. Services Ltd | 11/27/2022 | 270,185,099.25 | 256,675,844.90 | 85% | May-24 | |
| 5 | Electrification of Humbutudi | | Maiha LGA | Audu Gombi Investments Ltd | 9/10/2023 | 89,398,199.04 | 89,398,199.04 | 95% | May-24 | |
| 6 | Electrification of Maiha-Gari | | Maiha LGA | Ms Chale Nig Ltd | 9/10/2023 | 205,205,153.67 | 184,684,638.31 | 95% | May-24 | |
| 7 | Electrification of Gorobo and Dapanti | | Mayo-Belwa LGA | Mudaba Nig Ltd | 9/10/2023 | 155,914,940.71 | 140,323,446.28 | 90% | May-24 | |
| 8 | Electrification of Fahar, Kaulewa, Mbewa and Wuyaku | | Gombi LGA | Galaxy Rays Nig Ltd | 9/10/2023 | 192,676,258.10 | 154,141,007.28 | 100% | Apr-24 | Awaiting Official Commissioning |
| 9 | Electricity Supply to Cottage Hospital Shelleng | | Shelleng LGA | PRC Resources Ltd | 12/12/2023 | 34,582,200.70 | 34,582,200.70 | 15% | Aug-24 | |
| 10 | Electricity Supply to Cottage Hospital Guyuk | | Guyuk LGA | SWS Logistics | 12/12/2023 | 31,106,658.99 | 31,106,658.99 | 15% | Aug-24 | |
| 11 | Electrification of Yolde Kohi | | Yola South | Audu Gombi Investments Ltd | 2/8/2023 | 41,623,626.45 | 41,623,626.45 | 100% | Apr-24 | Awaiting Official Commissioning |
| 12 | Electrification of Hosere Bembee | | Yola South | Audu Gombi Investments Ltd | 2/8/2023 | 45,927,250.75 | 45,927,250.75 | 100% | Apr-24 | Awaiting Official Commissioning |